Construction meeting minutes template
Minutes built the way experienced PMs run them: every item numbered, old business carried forward until it is closed, and every action item with a name and a date next to it.
Free, no sign-up. Word format — free to use and adapt in your business.
How to use these minutes
Number items as meeting.item (e.g. 12.03 = meeting 12, item 3) and keep that number for the life of the item — it makes minutes searchable and stops issues from quietly disappearing between meetings.
Distribute within 24–48 hours with a standing note that the minutes stand as written unless corrections are raised by the next meeting. That one line turns the minutes into the agreed record of the project.
Attendees & distribution
| Name | Company | Role | Present (Y/N) |
|---|---|---|---|
+ 10 blank rows to fill in in the Word document
Old business
Carry every open item forward, with its original number, until it is marked closed in a meeting. Update the status each week — "no change" is a status too, and it is the one that gets items escalated.
| Item # | Description | Responsible | Status | Date raised |
|---|---|---|---|---|
+ 8 blank rows to fill in in the Word document
New business
Record the decision or outcome, not the whole discussion. If an item needs follow-up, it also gets a row in the action items table below.
| Item # | Description | Discussion / decision | Responsible |
|---|---|---|---|
+ 6 blank rows to fill in in the Word document
Action items
| Item # | Action | Owner | Due date | Status |
|---|---|---|---|---|
+ 8 blank rows to fill in in the Word document
Minutes discipline
- Minutes issued to all attendees and distribution list within 48 hours
- Every open item has a number, an owner and a due date
- Old business reviewed first, item by item, before new business
- Decisions recorded with who made them, not just what was decided
- Standing note included: minutes stand as written unless corrections are raised by the next meeting
- Next meeting date and time confirmed and noted
Common questions
Who should take meeting minutes on a construction project?
How soon after the meeting should minutes go out?
What is the difference between old business and new business?
What if someone disputes what the minutes say?
What makes a good action item?
More free templates
Daily log with weather, manpower by company, work performed, deliveries, delays and a photo log — everything a superintendent records at the end of the day.
OpenOne log for every submittal: spec section, item, responsible sub, submitted/returned dates and standard action codes — so nothing arrives on site unapproved.
OpenNumbered punch items by room and location with responsible trade, status, and a verified-by column — built for the walk and the closeout that follows.
OpenSkip the templates — let the AI write the draft
In Planium, the AI agent drafts daily reports, meeting minutes, RFIs and change orders straight from your project documents — you review and adjust.