Punch list template
A punch list that actually closes: every item numbered and located, assigned to one trade, and not marked done until someone walks it and signs the verified column.
Free, no sign-up. Word format — free to use and adapt in your business.
How to use this punch list
Walk the space room by room and write items so a trade can find and fix them without calling you: location, specific deficiency, and what "fixed" looks like. "Touch up paint, room 214, west wall, 3 spots at outlet height" closes; "paint touch-ups throughout" never does.
Every item gets exactly one responsible trade. An item is not complete when the trade says it is — it is complete when someone walks it and signs the verified column. Keep completed items on the list, marked verified, as the record of closeout.
Punch list items
| Item # | Room / location | Description of deficiency | Responsible trade | Status | Completed (date) | Verified by / date |
|---|---|---|---|---|---|---|
+ 18 blank rows to fill in in the Word document
Status conventions
| Status | Meaning |
|---|---|
| Open | Identified, not yet corrected |
| In progress | Trade is actively working the item |
| Complete | Trade reports the item corrected — awaiting verification |
| Verified | Walked and accepted — signed in the verified column |
| Disputed | Trade disputes responsibility or scope — escalate, do not let it sit |
Closing out the punch list
- Items written with room number, specific location and specific deficiency
- Each item assigned to exactly one responsible trade
- Trades given a copy the same day as the walk, with a completion deadline
- Completion status updated as trades report items done
- Every completed item re-walked and signed in the verified column
- Disputed items escalated within days, not parked
- Final signed list filed with the closeout documents
Sign-off
When every item is verified, close the list formally — it is a common condition for final payment and release of retainage.
| Role | Name | Signature | Date |
|---|---|---|---|
| General contractor | |||
| Owner / owner’s representative | |||
| Architect / engineer |
Common questions
What is a punch list in construction?
Who creates the punch list?
What is the difference between the punch list and substantial completion?
How do punch list items get closed?
What if a sub disputes a punch item?
More free templates
One log for every submittal: spec section, item, responsible sub, submitted/returned dates and standard action codes — so nothing arrives on site unapproved.
OpenDaily log with weather, manpower by company, work performed, deliveries, delays and a photo log — everything a superintendent records at the end of the day.
OpenProgress / OAC meeting minutes with attendees, old business carried until closed, new business, and action items with owner and due date.