Change order form template
A change order form that leaves nothing to argue about later: what changed and why, an itemized cost breakdown, the running contract total, the schedule impact in calendar days — and signatures before the work is buried.
Free, no sign-up. Word format — free to use and adapt in your business.
How to use this form
One change order per change, numbered sequentially, with the scope described precisely — including what is added, what is deleted, and which drawings, RFIs or directives the change stems from. Vague scope descriptions are where change order disputes start.
Get signatures before performing the work whenever the contract allows. Work performed on a verbal "go ahead" is the classic unpaid change order — if you must proceed, at minimum confirm the direction in writing the same day and follow your contract’s notice provisions.
Description of change
| Describe the change in scope (what is added / deleted, with drawing, RFI or directive references) |
|---|
+ 6 blank rows to fill in in the Word document
Reason for change
- Owner-requested change
- Design change / clarification (revised drawings, RFI response)
- Unforeseen / differing site condition
- Code or authority-having-jurisdiction requirement
- Correction of error or omission in the documents
- Schedule acceleration or resequencing directed by owner
- Other (describe in the description of change)
Cost breakdown
Itemize the pricing so it can be reviewed line by line. Markup percentages for overhead and profit are typically set by the contract — enter yours.
| Description | Labor | Material | Equipment | Subcontract | Total |
|---|---|---|---|---|---|
| Subtotal | |||||
| Overhead & profit ( ___ %) | |||||
| Bond / insurance ( ___ %) | |||||
| TOTAL — this change order |
Contract summary & schedule impact
| Item | Amount / days |
|---|---|
| Original contract amount | $ |
| Net change by previously approved change orders | $ |
| Contract amount prior to this change order | $ |
| This change order — add / (deduct) | $ |
| New contract amount including this change order | $ |
| Contract time change — add / (deduct), calendar days | |
| Revised substantial completion date |
Approvals
When signed by both parties, this change order amends the contract for the scope, price and time stated above.
| Role | Name | Signature | Date |
|---|---|---|---|
| Contractor | |||
| Owner / owner’s representative | |||
| Architect / engineer (where required) |
Common questions
What is a change order in construction?
Do I need a signed change order before doing the work?
What is the difference between a change order and a construction change directive?
What should the cost breakdown include?
How should schedule impact be handled in a change order?
More free templates
A clean RFI form: numbered, referenced to spec and drawings, with a suggested answer, a response block and cost/schedule impact flags.
OpenDaily log with weather, manpower by company, work performed, deliveries, delays and a photo log — everything a superintendent records at the end of the day.
OpenProgress / OAC meeting minutes with attendees, old business carried until closed, new business, and action items with owner and due date.
OpenSkip the templates — let the AI write the draft
In Planium, the AI agent drafts daily reports, meeting minutes, RFIs and change orders straight from your project documents — you review and adjust.