RFI template — request for information
An RFI form that gets answered: one question per RFI, precise references, a suggested answer that makes the reviewer’s job easy, and impact flags so nobody can say later they didn’t know it mattered.
Free, no sign-up. Word format — free to use and adapt in your business.
How to use this RFI
One question per RFI. Bundling three questions into one form guarantees a partial answer and an item nobody can close. Reference the exact sheet, detail and spec paragraph — a reviewer who has to hunt for the conflict answers slower and worse.
Set a realistic response-needed-by date tied to the schedule, and say what the date is driven by. Then track every RFI on a log with submitted and answered dates — unanswered RFIs are one of the most common documented causes of delay.
Question / information requested
Describe the conflict, gap or ambiguity in the contract documents. State what you checked (sheets, details, spec sections) and where they disagree or fall silent.
| Question (describe the conflict or missing information, with exact references) |
|---|
+ 6 blank rows to fill in in the Word document
Contractor’s suggested answer
Propose a solution whenever you can. A suggested answer speeds up review, shows you have thought it through, and often gets adopted verbatim — which means the answer you can build.
| Suggested answer / proposed solution |
|---|
+ 4 blank rows to fill in in the Word document
Response
To be completed by the architect / engineer. A response that changes the scope, cost or time of the work is not just an answer — see the impact section below.
| Response |
|---|
+ 6 blank rows to fill in in the Word document
Cost & schedule impact
Flag potential impact when the RFI is submitted, not after the answer arrives. If the response changes cost or time, follow your contract’s change process — an RFI answer by itself is generally not a change order.
| Impact | None expected | Potential impact | Description |
|---|---|---|---|
| Cost | ☐ | ☐ | |
| Schedule | ☐ | ☐ |
Closeout
| Field | Entry |
|---|---|
| Responded by (name / firm) | |
| Date answered | |
| Distribution (who needs this answer in the field) | |
| Follow-up required (change order, revised drawing, none) |
Common questions
What is an RFI in construction?
How long does the architect have to respond to an RFI?
Should the contractor include a suggested answer?
Can an RFI response change the contract price or schedule?
What makes a bad RFI?
More free templates
Change order form with description and reason for change, itemized cost breakdown, contract summary, schedule impact and signature block.
OpenDaily log with weather, manpower by company, work performed, deliveries, delays and a photo log — everything a superintendent records at the end of the day.
OpenProgress / OAC meeting minutes with attendees, old business carried until closed, new business, and action items with owner and due date.
OpenSkip the templates — let the AI write the draft
In Planium, the AI agent drafts daily reports, meeting minutes, RFIs and change orders straight from your project documents — you review and adjust.