Tildelt

Contract award sub-contract 07 Ground and foundations FOR CO2 Terminal

HAFSLUND CELSIO AS

Tildeling

Vinner
Consto Anlegg Øst AS
Kontraktsverdi
86 451 161 kr
Antall tilbud
10

Beskrivelse

A complete CO2 shipping terminal shall be constructed at the Oslo Port in connection with the establishment of the carbon capture facility at Klemetsrud. The terminal will i.a. consist of CO2 unloading stations, storage tanks and loading arms for loading ships. Comprehensive civil work is required for this project. A Joint Venture between Aker Solutions and SLB Capturi will through its EPCIC contract with Hafslund Celsio be the Contract Manager (hereafter called the EPCIC supplier). The following work is included in the delivery: Rigging and operation, general servicesFounds and foundations Pipes in the groundBetong workExtro-installationsDoor ́s foundations for process equipmentPorts and fence participation in systematic completion led by the EPCIC supplier List above is not exhaustive, but covers the most important elements in the sub-contract.

  • 45200000 Works for complete or part construction and civil engineering work
  • 45000000 Construction work
  • 45255300
  • 45262300 Concrete work
  • 45300000 Building installation work
  • 45311000
  • 45312100
  • 45314300
  • 45316000 Installation work of illumination and signalling systems
  • 45317000 Other electrical installation work
  • 45320000
  • 45330000 Plumbing and sanitary works
  • 45332000 Plumbing and drain-laying work
  • 45340000
  • 45341000
  • 45342000
  • 45343000
  • 45400000 Building completion work

Flere konkurranser

Anbud Norge

Les konkurransegrunnlaget på minutter, ikke timer

Last opp konkurransegrunnlaget i Planium og få kravmatrise, risikoer og en go/no-go-vurdering fra AI. Gratis å komme i gang.

Kilde: TED (Tenders Electronic Daily), EUs publikasjonskontor — kunngjort via Doffin. Gjenbruk etter kommisjonsbeslutning 2011/833/EU. Oppdatert 12. oktober 2026.