Contract award sub-contract 06 Technical buildings and foundations

HAFSLUND CELSIO AS

Tildeling

Vinner
AF Gruppen Norge AS
Kontraktsverdi
520 814 585 kr
Antall tilbud
8

Beskrivelse

A complete technical building shall be constructed for process equipment and accompanying technical installations for the operation of the carbon capture plant in connection with the establishment of the carbon capture facility at Klemetsrud. A Joint Venture between Aker Solutions and SLB Capturi will through its EPCIC contract with Hafslund Celsio be the Contract Manager (hereafter called the EPCIC supplier). The contract is an execution contract regulated by NS8405 with Hafslund Celsio ́s special contract terms. Contracting was signed 07 October 2025. The construction start is estimated to Q4 2025 and the hand over business Q4 2028.

  • 45200000 Works for complete or part construction and civil engineering work
  • 45252300
  • 45300000 Building installation work
  • 45311000
  • 45312100
  • 45313100 Lift installation work
  • 45314300
  • 45316000 Installation work of illumination and signalling systems
  • 45317000 Other electrical installation work
  • 45320000
  • 45330000 Plumbing and sanitary works
  • 45332000 Plumbing and drain-laying work
  • 45340000
  • 45341000
  • 45342000
  • 45343000
  • 45400000 Building completion work

Flere konkurranser

Anbud Norge

Les konkurransegrunnlaget på minutter, ikke timer

Last opp konkurransegrunnlaget i Planium og få kravmatrise, risikoer og en go/no-go-vurdering fra AI. Gratis å komme i gang.

Kilde: TED (Tenders Electronic Daily), EUs publikasjonskontor — kunngjort via Doffin. Gjenbruk etter kommisjonsbeslutning 2011/833/EU. Oppdatert 12. oktober 2026.