Awarded

Orkney Community Wind Farms (OCWF) - Balance of Plant Contract

Orkney Islands Council

Award

Supplier
Heddle Construction Ltd
Contract value
Not stated

Description

Orkney Islands Council (OIC) is developing Orkney Community Wind Farms, comprising two windfarms in the Orkney Islands. Quanterness wind farm, located on Mainland Orkney (Northwest of Kirkwall), consisting of six circa 4.8 MW Wind Turbine Generators. Faray wind farm, located on the uninhabited island of Faray in the North isles, consisting of six circa 4.8 MW Wind Turbine Generators. Both wind farms have obtained all planning consent and grid connection agreements. Quanterness is due to commence operation in June 2028, with Faray commencing operation in May 2030.

  • 45200000 Works for complete or part construction and civil engineering work
  • 45220000 Engineering works and construction works
  • 45223500 Reinforced-concrete structures
  • 45232200 Ancillary works for electricity power lines
  • 45232220 Substation construction work
  • 45233226 Access road construction work

More tenders

Tenders United Kingdom

Read tender packs in minutes, not hours

Upload the tender documents to Planium and get a compliance matrix, risks and a bid/no-bid recommendation from AI. Free to start.

Source: Find a Tender Service — UK Cabinet Office. Open Government Licence v3.0. Updated 12 October 2026.